On Track and On Schedule
Here are the highlights:
HUB:
- Main School site (the “hub”) wire frame is complete
- University Marketing has commenced development of Hub site mock-ups. These mock-ups will be used to undertake reviews /approvals with stakeholders, before University Marketing begins development of the Hub site.
C&I:
- The C&I department site wire frame is complete
- We have begun development of the site prototype. The C&I prototype will be used to undertake reviews/approvals with C&I in early October. A pre-launch go/no-go meeting is scheduled with C&I on 12/13.
Common vs. Flexible Elements & News & Events:
- We have completed meetings with all department Chairs regarding the common vs. flexible elements of the department sites.
- We have completed meetings with all department Chairs regarding the functionality of the news & events elements.